Subcontracting costs: what if they have been misestimated in Annex I? Is there a % tolerance?

Answer: 
The rule is that the tasks to be implemented and the estimated cost for each subcontract must be set out in Annex 1, and the total estimated costs of subcontracting per beneficiary must be set out in Annex 2. The actual price may be higher or lower than the estimation in the budget. There is no ‘% tolerance’ foreseen.Nike Air Jordan 1 Retro